1. What was the reason of
proposing to replace the existing Connectivity/ Long Term Access/Medium Term
Open Access regulations with General
Network Access (GNA) Regulations?
Central Electricity Regulatory Commission
vide its two orders issue in March, 2010 and Feb, 2011 grant approval for
Eleven High Capacity Transmission corridors of cost around Rs. 50,000 Cr for
evacuation of power of Generation projects of IPPs. The progress of these IPP-projects
was affected due to various reasons like delay in land acquisition, statutory
clearance and fuel tie up. Due to issues related to case–I bidding not many
distribution companies have tied up their power requirement from these generating
stations. There being no liability for payment of transmission charges
associated with Connectivity. Some of the generators were seeking LTA for a
quantum much less than their Connectivity to piggy ride
on the existing transmission network avoiding the liability of paying monthly
transmission charges which would be payable under LTA service. Naturally,
inter-State Transmission Charges for these stranded lines has been shared by end-users
who have little say in such capacity building. As these generators do not have
any firm beneficiaries, it is difficult to plan proper transmission system
which results congestion in some section. CTU and CEA raised concern in regard
to the present mechanism of treating Connectivity and Long Term Access
separately. Besides, it is often found that the drawal requirement of
many states is more than the allocated power. Transmission system so created to
meet the drawal requirement of the states fulfills the need of that particular
State; however, the charges are shared by all the beneficiaries. Further, availability of National Grid facilitates
transfer of power from available cheaper sources. This has opened up
opportunities for economic despatch of stations. Many States are backing down
their own generating stations or not scheduling power from costlier ISGS and
buying power from other sources through MTOA/STOA. The present transmission
planning process does not incorporate economic despatch principle. In this situation, CEA initiated the idea of GNA for (i) proper planning
of Transmission system and (ii) assured recovery of transmission charges from
the applicant. States like Punjab, Tamil Nadu, Haryana, Uttar
Pradesh etc. who are availing far more import capacity through ISTS than their
LTA capacity should proportionally share the PoC charges at the point of
drawal. It needs to be recognized that in the current scenario if short term/
medium/PX transactions are curtailed it results in significant bottling up of
generation and distress to DISCOMs.
2.
What
is the basic difference between ‘existing practice’ and ‘GNA approach’ in
respect of planning? Transmission Planning is presently being done on the basis
of Long Term Access (LTA) taken by ISGSs. Load-Generation
balance is being done on the basis of
Electric
Power Survey published by CEA. Transmission
Planning is proposed to be done on the basis of projected load of the States
and anticipated generation scenario based on economic principles of merit order
operation. Clause 19.1(a) of draft Planning Regulation lays the objective of
planning as “To plan transmission system for optimal utilization
of resources to subserve the interests of the national economy with due
consideration to power market.
3.
What benefit planners shall get from GNA? Transmission system strengthening to be carried out based on
GNA requirements of the generators and the States and in accordance with the CEA (Technical Standards for
Connectivity to Grid) Regulation.
With GNA figures planners can achieve a much more practical planning.
4.
What
is the proposed definition of GNA? “General
Network Access or GNA” means the non-discriminatory access to the ISTS granted
by the CTU to an Applicant for an estimated maximum injection/ drawal for a
specified period.
5.
What is the
proposed concept of GNA? GNA is the ability in MW to draw or supply from a given point/zone of
connection (PoC) to any ISTS point as assessed by the CTU through system
studies.
6.
In what way proposed GNA is different from Long
Term Access or Medium Term Open Access?
“Long Term Access or LTA” means the right to use the inter-State Transmission
system for a period exceeding 7 years and “Medium Term Open Access or MTOA”
means the right to use the inter-State Transmission system for a period equal
to or exceeding 3 months but not exceeding 5 years. LTA is allowed on the basis
of MW applied for power transaction from source to drawal point/targeted region
whereas GNA shall be allowed on the estimated (by CTU) max injection/drawal of
a node/zone for a specified period and not on considering source to drawal
point route.
7.
Shall the term LTA and MTOA exist after
commencement of proposed GNA? (i)
On commencement of CERC (Grant of Connectivity and GNA to the ISTS and other
related matters) Regulations, the CERC (Grant of Connectivity, LTA and MTOA in
ISTS and related matters) Regulations 2009 shall stand repealed.
(ii) Long-term access or medium term
open access granted in accordance with the Central Electricity Regulatory
Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access
in inter-State Transmission and related matters) Regulations, 2009 (as amended
from time to time) shall continue to be valid till GNA is granted for such
access by CTU as per these Regulations.
8. What is the chronology of the development of draft GNA
Regulations?
Chronology of development of GNA Regulations is as given below:
(i)
December
2013: Concept of GNA by CEA was placed.
(ii)
September 2014: Staff Paper released by
CERC on Planning, Connectivity, LTA, MTOA
(iii)
February 2016: Report of Task Force (formed
by CERC) with draft Planning Regulations
(iv)
September 2016: Publication of Mata Prasad
Committee (formed by CERC) Report with proposal for GNA
(v)
26.04.2017: Draft Regulations on Planning
by CERC considering Task Force and Mata Prasad Committee Report and proposed to
delete Part-III of IEGC
(vi)
14.11.2017:
Draft Central Electricity
Regulatory Commission (Grant of Connectivity and General Network Access to the
inter-State transmission system and other related matters) Regulations, 2017
9.
What benefit
generators shall get from proposed GNA? Following are
the benefits generators shall get: (i) Generators shall not be liable to pay
notional point of drawal charges (ii) Generators shall not have to declare
target beneficiaries (iii) More than one
generator can use the dedicated transmission line connecting their generating
station to pooling station of ISTS. An “Applicant for Connectivity” may be
connected to both inter-State transmission system and intra-State transmission
system.
10.
What difficulty the generators shall experience due to proposed
GNA Regulations? GNA of generators will be Installed capacity less auxiliary consumption. There is a
provision of Bank Guarantee of Rs. 20 Lakhs/MW GNA sought. In case GNA customer
intends to exit from GNA he shall be liable to pay relinquishment charges.
Generators have to apply for GNA within two and half years of grant of
connectivity, failing which connectivity will deem to be cancelled.
11.
What benefit distribution licensees shall
get from proposed GNA Regulations?
Distribution Licensee who intends to avail supply for a minimum load of 250 MW
from the inter-State transmission system shall be treated as eligible for inter-State
connectivity.
12.
What benefit Bulk Consumers shall get from proposed
GNA Regulations? Consumer who
intends to avail supply for a minimum load of 250 MW from the inter-State
transmission system shall be treated as eligible for inter-State connectivity.
13.
What is the relation between proposed GNA and PoC charges? The concept of PoC charges has de-linked the transmission charges and
losses from the notional path of commercial transaction of power. GNA is also
not path specific. Accordingly, charges for GNA could be aligned with the PoC
mechanism. Para 6(c) of Mata Prasad Committee Report suggests that “An Applicant should be charged with Reliability charges
for connected quantum”.
14.
What is the special provision in proposed GNA
Regulations for Day Ahead Collective Transactions? 5% of each corridor for which separate ATC is declared
shall be reserved for day ahead collective transaction. NLDC shall release the
capacity for contingency market in case of non-utilization by power exchanges.
15.
What are the salient features of draft GNA
Regulations in respect of States? Salient features of draft GNA
Regulations in respect of States are:
(i)
State
transmission utilities acting on behalf of distribution licensees and other
intra-state entities that are seeking GNA to ISTS would need to apply for GNA
each year for a five-year period.
(ii)
CTU will allocate GNA based on system studies.
(iii)
Deviation charges shall be as per
CERC (Deviation Settlement Regulations) 2010. 2010Unless specified otherwise by
the State Commission concerned, the Deviation rate for intra-State entity shall
be 105% (for over-drawals or under generation) and 95% (for under-drawals or
over generation) of the Deviation rate at the periphery of regional entity.
(iv)
STUs shall not be required to submit
Access Bank Guarantee.
(v)
Any intra-State entity desirous of availing
GNA to ISTS may apply GNA application directly to CTU alongwith required No
objection certificate from STU or it may apply for the same to STU. STU shall
consider such GNA application by all intra-state entities while making
application on behalf of intra-State entities for grant of GNA to CTU.
(vi)
Unless specified otherwise by the
State Commission concerned, the Deviation rate for intra-State entity shall be
105% (for over-drawals or under generation) and 95% (for under-drawals or over
generation) of the Deviation rate at the periphery of regional entity.
(vii)
In case of allocation of power by
Ministry of Power, Govt. of India in respect of generating stations owned or
controlled by Central Government, the concerned generating company may make
application to CTU for GNA on behalf of the allocatees on the basis of their
written authority for making the application.
(viii)
CTU shall approach the Central
Commission for regulatory approval along with system studies of new transmission
assets in respect of ISTS within a month of its approval by Standing Committee.
After the approval is accorded by the Central Commission, the system
strengthening of ISTS shall be undertaken for implementation in accordance with
applicable Regulations.
****
Comments
Post a Comment