1. What was the reason of proposing to replace the existing Connectivity/ Long Term Access/Medium Term Open Access regulations with General Network Access (GNA) Regulations? Central Electricity Regulatory Commission vide its two orders issue in March, 2010 and Feb, 2011 grant approval for Eleven High Capacity Transmission corridors of cost around Rs. 50,000 Cr for evacuation of power of Generation projects of IPPs. The progress of these IPP-projects was affected due to various reasons like delay in land acquisition, statutory clearance and fuel tie up. Due to issues related to case–I bidding not many distribution companies have tied up their power requirement from these generating stations. There being no liability for payment of transmission charges associated with Connectivity. Some of the generators were seeking LTA for a quantum much less than their Connectivity to piggy ride on the existing transmission network avoiding the liability of paying monthly transmissi...